What method uses time buffers?

1
0
-1

What method uses time buffers to ensure that feeder activities don’t extend the project duration?

784 views.
Answer
1 answer

This one is the BEST answer!
1
+1
-1

The critical chain method uses time buffers inserted into the project schedule to ensure that high-risk activities do not cause the overall project duration to extend.