What are the two types of justifiable reserve that may be used on a project?
15 points
Contingency Reserve & management Reserve
18 points
Both the contingency reserve, for “known unknowns,” and the management reserve, for “unknown unknowns,” are developed by using quantitative data and historical information and, therefore, provide justifiable reserves