Under what conditions would you generally choose to use a time and materials contract?

1591 views.
Answer
2 answers

This one is the BEST answer!
1
0
-1

You would generally choose to use a time and materials form of contract when the work is small and ill defined, or under emergency conditions where the work must be completed quickly and there is not time to negotiate any other form of contract.

1
0
-1

When the project duration is short, when u need to outsource a project, when the scope is not well defined.